Mars Solar Get a Proposal

How to size battery storage for a commercial building

In short

Size storage from the load you want to keep running and for how long, not from your monthly electricity bill. The sequence is: list the circuits that must stay live and their kW, choose a backup duration, convert that to usable energy, then divide by the usable state-of-charge window to get nameplate capacity. The converter is sized separately, from peak and starting current.

Open battery rack with stackable modules
Battery rack with stackable modules. The shipped model and its datasheet are issued with the order.

The method, in four steps

  1. 01

    List the critical circuits

    Not the whole building. Walk the distribution board and mark each circuit as critical, deferrable or abandonable during an outage. Record kW for each. This list is the foundation of every number that follows, and it is the step most often skipped.

  2. 02

    Choose a backup duration

    This is a commercial decision, not an engineering one. Two hours covers the gap between grid failure and generator start; six hours covers an overnight outage. Ask the client what failure they are insuring against, then write the number down — because it is the largest single driver of cost.

  3. 03

    Convert to usable energy

    Usable energy = critical load (kW) × duration (h) ÷ converter efficiency. Divide the result by the usable state-of-charge window to get nameplate capacity. The window is typically 80–90% for a new LFP system, and narrower if the design reserves capacity for backup.

  4. 04

    Size the converter separately

    The converter is sized on peak load and starting current, not on energy. A system can have enough kWh and still trip, because the inverter cannot supply the starting current of a compressor. These are two independent checks and both must pass.

The formula, written out.
Usable energy (kWh) = critical load (kW) × duration (h) ÷ inverter efficiency
Nameplate capacity (kWh) = usable energy ÷ usable state-of-charge window

Every term in that formula is project-specific. That is why a runtime figure quoted without the assumptions behind it cannot be checked — and why we do not quote one.

Worked example

A commercial building with 60 kW of critical load, a two-hour requirement, 92% inverter efficiency and an 85% usable window:

StepCalculationResult
Energy delivered to load60 kW × 2 h120 kWh
Account for conversion loss120 ÷ 0.92130.4 kWh drawn from the battery
Account for usable window130.4 ÷ 0.85153.4 kWh nameplate
Converter checkPeak load, not averageConverter ≥ peak, plus starting margin

This is an illustration of the method, not a recommendation for your site. The two percentages above are assumptions; your design may use different ones, and the datasheet governs.

The assumptions that change the answer

AssumptionEffect if you take it too optimistically
Usable state-of-charge windowSystem runs out earlier than the design intends
Inverter efficiency at partial loadEfficiency is lower at light load; a nominal figure overstates output
Ambient temperatureHigh cell temperature reduces available capacity and accelerates ageing
Battery age at end of serviceCapacity fades; a system sized to new-cell capacity under-delivers in year five
Load growthThe critical load list is a snapshot; expansion erodes the margin
Starting currentMotor starts can trip a converter that is correctly sized on energy

What sizing cannot fix

What we need to do this for you

Send four things: the load schedule with critical circuits marked, the backup duration you are designing to, the site country and grid status, and the highest ambient temperature the equipment room reaches. With those, the calculation above can be run against your project instead of an example.

Send your load schedule
Get a Proposal WhatsApp